Fully Fuzzy Time-Cost Trade-Off in a Project Network - A New Approach
Abstract
In this paper, we propose a new approach to Fuzzy network crashing in a project network whose activity times are uncertain. The uncertain parameters in the project network are represented by triangular fuzzy numbers. By using a new type of fuzzy arithmetic and a fuzzy ranking method we propose a method for finding an optimal duration by crashing the fuzzy activities of a project network without converting the fuzzy activity times to classical numbers. A numerical example is provided to illustrate the proposed method.
Keywords: Triangular fuzzy number, fuzzy ranking, fuzzy project network, Critical path, crashing.
To list your conference here. Please contact the administrator of this platform.
Paper submission email: MTM@iiste.org
ISSN (Paper)2224-5804 ISSN (Online)2225-0522
Please add our address "contact@iiste.org" into your email contact list.
This journal follows ISO 9001 management standard and licensed under a Creative Commons Attribution 3.0 License.
Copyright © www.iiste.org